H. Case Studies
The following is a selection of case studies that illustrate application of the principles and thought process behind CSD/CSS. The case studies were assembled from materials and interviews conducted with pilot state representatives, as well as with other agencies contacted during the research project. The case studies are geographically diverse. They illustrate a wide range of project contexts, from rural roads to urban streets. They demonstrate that one can be context sensitive when dealing with a freeway, an arterial, or a local road. In one case, they show that the mission of a transportation agency can and should go beyond providing for safe and efficient transportation. They represent both small projects and substantial efforts.
Most of all, the case studies show how project success can be achieved by following the framework discussed here, and applying the right resources to solve a problem.
Jump to: Case Study 1 | Case
Study 2 | Case Study 3 | Case
Study 4 | Case Study 5 | Case
Study 6 | Case Study 7 | Case
Study 8 | Case Study 9
Case Study No. 1 Merritt Parkway Gateway Project Greenwich, Connecticut
Setting
The Merritt Parkway (the Parkway) was constructed in the 1930s and opened to
traffic in 1940. The facility, a four-lane divided arterial highway, was
originally designed and continues to function as an essential component
of Connecticut's transportation system.
The Parkway has long been recognized for its unique design features and
scenic character. Its park-like setting, majestic bridges, and scenic
landscaping make it a distinct and appreciated asset to the state. The
bridge architecture utilizes motifs that were popular in the 1930s, including
Art Moderne, Art Dec, Classical, Gothic, and Renaissance.
The
Parkway was placed on the National Register of Historic Places in 1991,
and in 1993, was designated a State Scenic Road. In 1996, it achieved
designation as a National Scenic Byway.
When first constructed, the land use through which the Parkway was built
was primarily rural, agricultural, and open space uses. Over time, the
landscape has matured and changed. Development has occurred in the vicinity
of the Parkway, bringing with it both increased traffic and residences
near the Parkway.
Both the volume of traffic and its character and operations have changed
over time. The Parkway now carries traffic in excess of 50,000 vehicles
per day in some segments. Originally designed for speeds prevalent in
the 1930s (35 to 40 mph), it now operates at speeds in excess of 60 mph,
and with greater density of traffic. The Parkway has evolved into now
serving as a commuter route.
Not surprisingly, the substantive safety history of the Parkway has become
an increasing concern to the Connecticut DOT. Both the terrain and context,
as well as the character of the original design, produce relatively high
risk of severe roadside collisions with obstacles such as trees and rock
outcropping. Shoulders are typically only 2 feet wide, and clear areas
and offsets to fixed objects generally less than 6 feet. The narrow median
was not originally designed with a physical barrier. The heavier traffic
and speeds greater than the Parkway was designed for are also issues of
concern.
From 1986 through 1990, there was one reported crash every 8 hours, one injury
every 20 hours, one fatality every 52 days, and a guide rail struck every
36 hours along the 38-mile corridor. This alarming history of both frequent
and severe crashes indicated a need for action.
Problems to be Solved
The problems to be solved were improving the safety and operational efficiency
of the Parkway while maintaining its unique and valued characteristics.
Related to these problems were resolving the long-term role of the Parkway
relative to development and its attendant pressures, and with respect
to other transportation system features in the area.
These problems were articulated in a series of questions and issues developed
by a stakeholder working group that was convened by the Connecticut DOT.
- The Parkway's future as it relates to its capacity to carry vehicles
cannot be separated from the land uses allowed or encouraged by local
zoning entities and towns.
- Pressures for an expanded transportation facility and the desire
for increased local development are not separate and unrelated. The
future of the Parkway was viewed as being inextricably driven by the
land use decisions made by towns and others.
- A fundamental question to be resolved (a choice to be made) was stated
simply - Is the Merritt Parkway a major transportation facility or is
it simply a beautiful place?
The project in which these issues were addressed involved the development of
guidelines for resurfacing, safety improvements, and enhancement projects
for the Parkway. These guidelines would in effect provide firm direction
for the scope, nature, and types of improvements considered appropriate
for the Parkway over the long term.
Stakeholders
- Connecticut Department of Transportation
- Fairfield County, CT
- Merritt Parkway Working Group (comprised of DOT staff in engineering,
traffic, landscape design, maintenance, construction and planning; outside
experts in architecture and preservation)
- Local town officials
- General public
CSD/CSS Approach
Much work and many meetings were held to wrestle with the conflicting issues
of providing for safety (and in particular, roadside safety) and maintaining
landscaping and other visual features. Extensive research was conducted,
including thorough site reviews and interviews with the original landscape
architect, W. Thayer Chase, to fully understand and confirm his philosophies
and intentions.
Deliverables to be used by the DOT included 'Merritt Parkway Guidelines'
and 'A Landscape Master Plan For the Merritt Parkway.'
Design Flexibility and the Application of Design Criteria
The Connecticut DOT, through its Merritt Parkway Working Group, in effect established
corridor-specific design criteria that reflected the consensus best efforts
to balance safety and aesthetic considerations.
- The DOT chose a design speed of 60 mph for the facility, intending
to post a 50 mph legal speed limit.
- The DOT chose not to view the Parkway as a route to be used for increasing
through regional east-west capacity.
- The DOT chose to address the safety issue by focusing primarily on
roadside crash severity. Design solutions (see attached typical sections)
incorporated 4-foot shoulders and enhanced crash tested barrier systems
that were visually less obtrusive than standard guiderail. Barrier or
rail was placed in the median depending on the presence of mature trees,
which for the most part were retained. Some rock outcroppings were selectively
removed, but the general overall roadside character was retained.
Note that, were this a new freeway or expressway, or a similar route in a different
context, the DOT would apply more stringent design criteria for the roadside.
The AASHTO Roadside Design Guide suggests up to 30-foot clear as a target
dimension from the edge of pavement, with mild slopes and free of obstacles.
Such a design, or use of continuous barrier, was not considered appropriate
for the context of the Parkway.
Part
of the design process was the development of a new, aesthetic median barrier.
To be acceptable, the barrier needed to pass vehicle crash tests based
on criteria established in NCHRP Report 350, which specifies speeds, angles
of collision, and vehicle types, as well as defines success or failure
in the testing. The DOT also selected a steel-back timber guide rail system
after researching many other systems. This unique system was also crash
tested to assure conformance with NCHRP Report 350 criteria.
Finally, detailed studies of crash types and locations were performed.
Based on these studies, selected high risk trees were removed, or identified
for preservation, but with protection afforded them.
As projects have been implemented, the DOT has monitored their performance.
A key measure, improvement in safety, has been successfully addressed.
Although the frequency of crashes has not decreased, the severity has.
In fact, this outcome could have been expected, as the placement of improved
barrier systems is intended to address severity and not crash frequency.
Stakeholder Involvement
The Working Group recommended establishment of a Merritt Parkway Advisory Committee.
This group would review actual design and other plans and assure their
conformance with the guidelines and master plan. (It was noted that in
some cases direction was vague, and in others contradictory. Location-specific
interpretation required some discussion.) Issues of long-term roadside
maintenance were reviewed and some changes made as a result.
Community involvement was extensive during development of the guidelines
and master plan. Elected officials helped identify key stakeholders. Issues
of invasive species, noise attenuation, visual effects, and loss of privacy
were discussed. Techniques included development of renderings to illustrate
design and landscaping concepts.
One group of stakeholders that in retrospect should have been included
but was not initially was construction experts. The close working areas
and special design features created unforeseen problems when the actual
individual projects were implemented. Based on construction experiences,
minor changes in design of curbing, rock outcropping removal, and other
features were made for future projects.
Public information meetings and workshops were held to explain the vision
and the approaches. These served to further highlight the attention of
the general public on the Parkway, its future, and the need for improvements.
Lessons Learned
This case study shows the importance of arriving at a vision or framework for
problem solving before developing the solution. In the case here, articulating
what the Merritt Parkway was (and was not) was necessary before beginning
design investigations.
Another
lesson learned was the importance of being flexible in the development
and use of design criteria. Also, addressing a safety problem with specific
actions is illustrated here. The key safety problem, severity of roadside
crashes, was directly addressed through a series of treatments. Also note
that a realistic view of what could be accomplished (a choice of aesthetics
over safety) should be a part of overall thinking and solution development.
A final lesson learned was the importance of involving construction and
maintenance staff in the development and evaluation of solutions.
Back to top
|